Highways chiefs have issued an overview on progress on the Bailgate improvement project and the work still to be done.

Achieved in February: 

  • Completed laying of all old and new setts with new mortar base and joints in Phase 1
  • Completed new road markings in Phase 1
  • Switched traffic management to Phase 2
  • Removed half of Phase 2 setts
  • Re-laid old and new setts in half of Phase 2 
  • Repaired four heritage street lighting columns 

What’s happening in March

  • Complete laying of old and new setts with new mortar base and joints in Phase 2
  • Switch traffic management to Phase 4A
  • Re-lay old and new setts in the whole of Phase 4A
  • Complete all road markings on Bailgate
  • Collaboration with National Grid to lay new power cable

Current/ongoing traffic restrictions and closures

  • 24/7 closure between Newport Arch and Westgate (Phase 2)

Upcoming traffic restrictions and closures

  • 24/7 closure of Westgate between Greggs and The Castle Hotel from mid-March to late May
  • No through-traffic outside of Westgate Academy starting w/c 13th April for one week
  • Closure of the section of Bailgate between Newport and Newport Arch starting w/c 20th April for up to two weeks, with local diversions onto Bailgate in place

Project phasing

  • Phase 1 – between Westgate and The White Hart Hotel
  • Phases 2 – between Newport Arch and Westgate
  • Phase 4A – Westgate between Greggs and The Castle Hotel
  • Phase 4B – between Newport and Newport Arch
  • Phase 5 – the raised crossing outside Westgate Academy 